Winton House Centre (WHC) moves forward undertaking substantial renovation works on the North Wing.  The first floor flat 1 will be merged with flat 2, to create a larger upgraded flat.  The merger will allow the stairs leading to flat 1 to be removed creating a considerable amount of extra usable space on the ground floor.

A new entrance into the Courtyard room removes the existing corridor, creating an additional room for hire.

The area currently occupied by Home Start Butser is to be redeveloped, providing meeting rooms, additional office space and accessible toilet. WHC are delighted to be able to continue our long-standing association with Home Start Butser and to assist in their development.

Plans for the development, can be viewed in the WHC Office, four local building companies have been invited to submit tenders.

Building work is expected to start in April with completion by the end of May 2020. There will be some disruption during the work, notably the unavailability of the courtyard room, and we are making alternative arrangements for regular users of the room whilst the work is in progress.